Leading a STM Medical Team


Overarching Principles


Trip Planning Timeline

Young ladies
Medical trips require great coordination of effort among many different processes or tasks. We have found it useful to divide the Pre-Trip planning time into early, mid, and late phase activities. The overall duration of the planning phase for a trip to Asia or Africa is very different, when compared to a trip to a Western hemisphere location. The table that follows provides an idea of the number of weeks prior to departure that a leader needs to be involved with or thinking about a particular activity.


This guide is organized with this timeline in mind. Some activities that the leader needs to be thinking about span the entire timeline from the beginning to the actual trip itself (logistics, for instance). Other activities are "on your plate" for a finite duration (booking air travel, for instance). Obviously, there is tremendous overlap and variation in the timing of these different activities and the table below presents a rough idea of when various issues become important.


Task Africa/Asia Latin America Border Country Quick Link
Prayer! 0 to 52 weeks 0 to 52 weeks 0 to 52 weeks
Partner selection 36 to 52 weeks 30 to 52 weeks 26 to 52 weeks Partner
Selection
Trip objectives 36 to 52 weeks 30 to 52 weeks 26 to 52 weeks Trip
Objectives
Trip dates 36 to 52 weeks 30 to 52 weeks 26 to 52 weeks Trip
Dates
Begin team interviews 26 to 48 weeks 26 to 48 weeks 18 to 48 weeks Team
Selection
Team STM applications 26 to 48 weeks 26 to 48 weeks 18 to 48 weeks
Visa required? 24 to 48 weeks 24 to 48 weeks n/a
Medical work
permit required?
24 to 48 weeks 24 to 48 weeks n/a
Immunizations
recommended?
26 to 48 weeks 26 to 48 weeks 18 to 48 weeks
Complete team selection 16 to 26 weeks 14 to 26 weeks 8 to 26 weeks Team
Selection
Verify valid passports 26 to 48 weeks 26 to 48 weeks 18 to 48 weeks
Purchase air travel 14 to 18 weeks 12 to 14 weeks n/a
Send medical work
permit applications
12 to 16 weeks 12 to 16 weeks n/a
Send letters
to supporters
12 to 16 weeks 8 to 16 weeks 8 to 16 weeks
First team meeting 12 to 16 weeks 8 to 14 weeks 6 to 12 weeks Team
Meetings
Send visa applications 8 to 14 weeks 8 to 14 weeks n/a
Budget finalized 8 to 12 weeks 6 to 12 weeks 4 to 10 weeks Budget
Development
Complete day to day
schedule
8 to 12 weeks 6 to 12 weeks 4 to 10 weeks Daily
Schedule
Order meds 4 to 8 weeks 4 to 8 weeks 4 to 8 weeks
Last team meeting 3 to 4 weeks 2 to 4 weeks 2 to 4 weeks Team
Meetings
Send off by church 1 to 3 weeks 1 to 3 weeks 1 to 3 weeks
Packing party 3 to 10 days 3 to 10 days 3 to 10 days
Depart On The Trip Depart Date! Depart Date! Depart Date!
Reunion dinner 2 to 4 wks
after return
2 to 4 wks
after return
2 to 4 wks
after return